Can the Owner make changes to the work?

Yes. The Owner may at any time order extra work or make changes by altering, adding to or deducting from the Contractor’s scope of work and within the general scope thereof; provided however that the changes do not exceed twenty five percent (25%). Such changes shall be ordered by the Owner in writing.

 

The issuance by the Owner of the revised Drawings or Supplemental Specifications changing the nature or work to be performed or of the materials to be provided shall be treated as sufficient written instruction of the Owner to the Contractor to execute the change.