What happens to the Contract if adjustments are required?

If there are any changes which shall lead to an increase or decrease in the amount due under the Contract, or in the time required for or manner of its performance, an equitable adjustment shall be made and the Contract modified accordingly. In the event that the Work is increased by such changes, the Contractor shall furnish proportionate additional performance bond.

 

In case where, without fault of the Contractor the Owner initiates a deductive change order for the purpose of transferring certain work items or part of the scope of work to another party or for the owner to supply certain construction materials, then the Contractor shall be entitled to 15% of deductive change order to recover his overhead and profit.