What must a Contractor do if he discovers discrepancy in the figures in the Drawings, and what is the consequence if he continues the Work notwithstanding the discrepancies?

The Contractor shall report to the Owner any discrepancy in the figures in the drawings immediately upon its discovery. The Owner shall make the necessary correction.

 

If the Contractor, without notifying the Owner of such discrepancy, performs his work according to the drawings notwithstanding such discrepancy, the Owner  may direct the Contractor to redo his work without an adjustment of his Contract Price and his Contract Time.