Who is responsible for providing storage space for the materials?

The Owner shall provide the Contractor, either at or near the project site, sufficient space for the Contractor's and Sub-contractors' use for storage of their materials and for erection of their sheds and tool houses.

 

The Contractor shall store all cement, lime, and other materials affected by moisture on platforms and protected from the weather. The materials shall be so stored as to ensure the preservation of their quality and fitness for the work. Stored materials shall be so located so as to facilitate prompt inspection.